Introduction


The Planning etc (Scotland) Act 2006 requires all Councils to prepare a Development Plan Scheme. This is a document that sets out our programme for preparing and reviewing the local plan. A copy of our most recent Development Plan Scheme 3 can be downloaded from the downloadable forms section on this page. The Development Plan Scheme 2 is updated annually. The Development Plan Scheme 3 provides information on the following issues:

  • The development plans we have now
  • Why we need to prepare a new Local Development Plan
  • The timetable for engaging people in the preparation of the plan and how we will do this  (the participation statement)
  • The timetable for preparing this plan (the project plan)

The table below sets out the key milestones in the production of the Local Development Plan:

Stage 1

 
Report Development Plan Scheme to committee Completed

Publish Development Plan Scheme

Completed

Process and Assess Development Options

Completed

Stage 2

 

Draft Main Issues Report and Strategic Environmental Assessment Scoping Report

Complete

Draft Monitoring Statement

Complete

Publish Main Issues Report and issue to persons and key agencies

Published - October 2009

Publish Monitoring Statement

Published - October 2009

Send Strategic Environmental Assessment Scoping Report to consultation authorities

Sent - October 2009

Stage 3

Process comments and Objections to the Main Issues Report

Complete

Prepare and publish Local Development Plan Scheme 2 and issue to Scottish Government

Complete

Prepare Proposed Aberdeen Local Development Plan

Complete

Prepare draft Action Programme

Complete

Prepare draft Environmental Report

Complete
Report to Full Council Complete - 18 August 2010

Printing Proposed Aberdeen Local Development Plan

September 2010

Publish Proposed Aberdeen Local Development Plan and notify to persons and key agencies

September 2010 (6 to 12 week consultation begins)

Publish Proposed Action Programme

September 2010

Publish Environmental Report and send to SEA Gateway under 2004 Regulations

September 2010

Notification of Neighbours

September 2010

Objection and representation period

September - November 2010


Stage 4

Consider Objections to Proposed Plan and draft Environmental Report

November 2010 – February 2011

Response to representations

March 2011

Report of Conformity with Participation Statement

March 2011

Print Aberdeen Local Development Plan

April 2011

Submit Proposed Plan, Action Programme and Statement of Conformity with Participation Statement (as modified if relevant) with Note of Representations and how taken account of to Ministers.

Publicise submission of plan

April 2011

Request Scottish Ministers to appoint an Examination of the Proposed Plan and Environmental Report

Advertise Examination of Proposed Plan and serve Notice on known interested parties

Examination (at least 4 weeks after request is made but likely to be longer)

Receive the Report of Examination

Likely to be 35 weeks after submission, i.e, December 2011


Stage 5

Consider recommendations and report to Planning Committee

February 2012

Publish Modifications and Proposed Plan as modified

March 2012

Advertise 'intention to adopt'

Notify each person who made representations of publication and intention to adopt

March 2012

The Aberdeen Local Development Plan is constituted as the local development plan (28 days after notification of intention to adopt) and Environmental Report

April 2012

Send two copies of the Aberdeen Local Development Plan and Environmental Report to Scottish Ministers

April 2012

Deposit copies of the Aberdeen Local Development Plan in libraries, notify each person who made representations and advertise it

April 2012

Publish Action Programme and Environmental Report Post Adoption Statement (within 3 months of adoption)

July 2012



 

Contacts

  • Development Plan Team
    Enterprise, Planning and Infrastructure
    Aberdeen City Council
    Business Hub 4
    Marischal College
    Broad Street
    Aberdeen
    AB10 1AB
    Phone: 01224 523330
    Fax: 01224 523180
    Email: ldp@aberdeencity.gov.uk