Content Related Links
Related Links
External Links
Aberdeen Local Development Plan - Timetable
Introduction
The Planning etc (Scotland) Act 2006 requires all Councils to prepare a Development Plan Scheme. This is a document that sets out our programme for preparing and reviewing the local plan. A copy of our most recent Development Plan Scheme 3 can be downloaded from the downloadable forms section on this page. The Development Plan Scheme 2 is updated annually. The Development Plan Scheme 3 provides information on the following issues:
- The development plans we have now
- Why we need to prepare a new Local Development Plan
- The timetable for engaging people in the preparation of the plan and how we will do this (the participation statement)
- The timetable for preparing this plan (the project plan)
The table below sets out the key milestones in the production of the Local Development Plan:
|
Stage 1 |
|
| Report Development Plan Scheme to committee | Completed |
|
Publish Development Plan Scheme |
Completed |
|
Process and Assess Development Options |
Completed |
|
Stage 2 |
|
|
Draft Main Issues Report and Strategic Environmental Assessment Scoping Report |
Complete |
|
Draft Monitoring Statement |
Complete |
|
Publish Main Issues Report and issue to persons and key agencies |
Published - October 2009 |
|
Publish Monitoring Statement |
Published - October 2009 |
|
Send Strategic Environmental Assessment Scoping Report to consultation authorities |
Sent - October 2009 |
|
Stage 3 |
|
|
Process comments and Objections to the Main Issues Report |
Complete |
|
Prepare and publish Local Development Plan Scheme 2 and issue to Scottish Government |
Complete |
|
Prepare Proposed Aberdeen Local Development Plan |
Complete |
|
Prepare draft Action Programme |
Complete |
|
Prepare draft Environmental Report |
Complete |
| Report to Full Council | Complete - 18 August 2010 |
|
Printing Proposed Aberdeen Local Development Plan |
September 2010 |
|
Publish Proposed Aberdeen Local Development Plan and notify to persons and key agencies |
September 2010 (6 to 12 week consultation begins) |
|
Publish Proposed Action Programme |
September 2010 |
|
Publish Environmental Report and send to SEA Gateway under 2004 Regulations |
September 2010 |
|
Notification of Neighbours |
September 2010 |
|
Objection and representation period |
September - November 2010 |
|
Stage 4 |
|
|
Consider Objections to Proposed Plan and draft Environmental Report |
November 2010 February 2011 |
|
Response to representations |
March 2011 |
|
Report of Conformity with Participation Statement |
March 2011 |
|
Print Aberdeen Local Development Plan |
April 2011 |
|
Submit Proposed Plan, Action Programme and Statement of Conformity with Participation Statement (as modified if relevant) with Note of Representations and how taken account of to Ministers. Publicise submission of plan |
April 2011 |
|
Request Scottish Ministers to appoint an Examination of the Proposed Plan and Environmental Report |
|
|
Advertise Examination of Proposed Plan and serve Notice on known interested parties |
|
|
Examination (at least 4 weeks after request is made but likely to be longer) |
|
|
Receive the Report of Examination |
Likely to be 35 weeks after submission, i.e, December 2011 |
|
Stage 5 |
|
|
Consider recommendations and report to Planning Committee |
February 2012 |
| Publish Modifications and Proposed Plan as modified |
March 2012 |
|
Advertise 'intention to adopt' Notify each person who made representations of publication and intention to adopt |
March 2012 |
|
The Aberdeen Local Development Plan is constituted as the local development plan (28 days after notification of intention to adopt) and Environmental Report |
April 2012 |
|
Send two copies of the Aberdeen Local Development Plan and Environmental Report to Scottish Ministers |
April 2012 |
|
Deposit copies of the Aberdeen Local Development Plan in libraries, notify each person who made representations and advertise it |
April 2012 |
|
Publish Action Programme and Environmental Report Post Adoption Statement (within 3 months of adoption) |
July 2012 |
Contacts
- Development Plan Team
Enterprise, Planning and Infrastructure
Aberdeen City Council
Business Hub 4
Marischal College
Broad Street
Aberdeen
AB10 1AB
Phone: 01224 523330
Fax: 01224 523180
Email: ldp@aberdeencity.gov.uk