3Rs Project - Timeline
History
| Date | Action |
|---|---|
| July 2002 | Aberdeen City Council agrees to seek funding support from Scottish Executive based on an NPDO (non-profit distributing organisation model |
| December 2002 | Outline Business Case submitted to Scottish Executive |
| March 2003 | Scottish Executive offers indicative support for the project |
| May 2004 | Revised Outline Business Case submitted to Scottish Executive |
| March 2005 | Contract notice published in Official Journal of European Community |
| September 2005 | Invitation to negotiate issued to three shortlisted approved bidders |
| April 2006 | ITN (Invitation To Negotiate) responses received |
| October 2006 | Council approves selection of Preferred Bidder |
| December 2006 | NYOP announced as Preferred Bidder |
| October 2007 | Begin construction on Cults Academy and Bucksburn Community Campus sites |
| December 2007 | Financial close (signing the contract) |
Projected Timetable
| Date | Action |
|---|---|
| Early 2008 | Work begins on Airyhall, Heathryburn & Mile End sites |
| Mid 2009 | First school, Heathryburn opens; Airyhall, Braehead & Mile End Schools open |
| Late 2009 | Hazlehead opens; Cults and Bucksburn Academy open |
| Early 2010 | Seaton School opens |
| Late 2010 | Manor Park & Kaimhill Schools open |